Repair and maintenance activities
The Company annually forms and executes the maintenance and repair program (MRO), taking into account:
- standard periodicity of capital;
- medium and current repairs of power equipment;
- technical condition of objects;the results of preventive tests;
- the need to comply with the Regulations of the supervisory authorities;elimination of technological violations;
- profitability and overall performance of electrical networks.
Description of the activities | 2016 | 2017 | 2018 | 2019 (planned) |
---|---|---|---|---|
Clearing of high-voltage lines, ha | 826.7 | 968.5 | 1,620.19 | 1,828.98 |
Replacement of ground wire, km | 72.7 | 130.4 | 77.08 | 77.25 |
Replacement of insulators, pcs. | 43,612 | 52,056 | 43,062 | 86,711 |
Repair of power transformers, pcs. | 26 | 41 | 21 | 21 |
Repair of switches, pcs. | 1,110 | 1,120 | 899 | 925 |
Repair of separators, short-circuit breakers, disconnectors, pcs. | 1,087 | 1,290 | 1,698 | 1,749 |
Repair of transformer substations, pcs. | 401 | 483 | 604 | 2,911 |
Repair of power lines, km | 2,764.3 | 2,888.0 | 3,124.3 | 12,467.9 |
To improve the reliability of the power grid complex by a comprehensive program to enhance the reliability of substation equipment, enhance the safety of
- reactive power sources recovered — 540 defective capacitors replaced;
- mechanical and electromagnetic interlocks were restored at 30 substations
35–110 kV; - there were replaced 57 physically worn
35–110 kV bushings, oil circuit breakers and power transformers; - thermovision inspection was performed:
- 508 OTL with the plan for 234 pcs.,
- 616 substations
35–110 kV, with the plan 288 pcs.;
- 763 power towers replaced by 10 kV overhead lines;
- there were replaced 2,011 towers with 0.4 kV overhead lines;
- 680.32 km of wire replaced with overhead transmission lines
0.4–10 kV; - 527.4 km of
0.4–10 kV bare wire replaced by steel insulated wire; - were replaced 14,640 branches to inputs to households made with bare wire;
- 11 overhead lines with uninsulated wires were removed from the territories of preschool institutions, schools, other educational institutions, camps, etc. (if the removal was impossible, the bare wire was replaced with insulated).
For 2019, the MRO expenditure limits were provided in the amount of 3,566.7 million rubles, which is 110% more than the 2018 plan, which let to form a set of measures in the MRO program, sufficient for the reliable electricity supply to Kubanenergo consumers.